Case Study
Caitlin’s Basement Remodel
- Cost: $65K
- Duration: 4 Weeks
The perfect recreational space for entertainment and hobbies.
Take a look at our newest basement remodel in Cary, NC! Watch how this dark and outdated basement turned into a brighter, more open, and more useful space!

PROJECT MANAGER
WILL ARMSTRONG

REMODELING SPECIALIST
RICH SCALZA
Project Overview



AFTER
BEFORE
The Vision
The vision for this project was to transform the basement from its original outdated look to a more updated, open and bright space.
Construction
This project followed our typical basement construction schedule:
- Demolition
- Framing
- Rough Plumbing
- Rough Electrical
- Rough HVAC
- Insulation
- Drywall
- Flooring
- Trim
- Paint
- Final Plumbing
- Final Electric
- Final HVAC
- Fixtures

Week 1
Demolition, Framing, Rough Mechanicals

Week 2
Insulation, Drywall, Flooring

Week 3
Trim, Paint, Final Mechanicals

Week 4
Fixtures & Touch-ups