Case Study
Erika’s Bathroom Remodel
- Cost: $20K-$25K
- Duration: 3 Weeks
A stunning bathroom remodel that blends modern design with luxurious comfort and natural light.
Take a look at our newest bathroom remodel in Cary, NC! Watch how this warm-toned, dark, outdated bathroom transformed into a sleek oasis.

PROJECT MANAGER
WILL ARMSTRONG

REMODELING SPECIALIST
RICH SCALZA
Project Overview
"We are extremely pleased with the work Oak City Remodeling did on our master bathroom remodel. One of the things that really stood out to us about Oak City Remodeling was the professionalism and courtesy of their proprietor, crew, and subcontractors. Despite being a small team, they were always available to answer any questions we had throughout the process and made sure to keep us updated on their progress. We never felt like we were in the dark about what was happening with the project. Additionally, the crew and subcontractors were consistently on time and arrived promptly each day they were scheduled to work. This made it easy for us to plan our own schedule around the renovation. Throughout the project we felt they were reliable and committed to completing the project on time. Oak City Remodeling was able to finish the project on time and on budget. Given the complexity of the project and the various subcontractors involved, we were initially worried that there would be delays or unexpected costs, but the team was able to stay on track and keep everything within the agreed-upon budget. In the end, the finished product exceeded our expectations and we are really enjoying our new master bathroom. We are looking forward to working with Oak City Remodeling again on future projects. We highly recommend Oak City Remodeling to anyone looking to renovate their home."
Erika, Bathroom Remodel










The Vision
The vision for this project was to give this outdated bathroom a modernized sense of luxury. By taking advantage of the natural lighting through brighter tile and finishes, we could transform it into a more open and breathable space.
Construction
This project followed our typical bathroom construction schedule:
- Demolition
- Rough Plumbing
- Rough Electrical
- Drywall Installation
- Tile
- Trim
- Paint
- Cabinet Installation
- Flooring
- Final Plumbing
- Final Electrical
- Accessories & Shower Door

Week 1
Demolition, Rough Mechanicals, and subfloor installation

Weeks 2 and 3
Drywall repairs and prepping for tile installation

Weeks 2 and 3
Vanity, flooring, and tile installation

Week 3
Finishing Fixtures & Touchups